November 18, 2026

BBC News: Home Office targets April opening for MOD Bicester asylum centre

BBC News reports that the Home Office is working towards opening the proposed asylum accommodation centre at MOD Bicester Site A in April 2027, despite ongoing legal challenges and significant concerns about the site’s readiness.

According to the report, published on 18 November 2026, Calum Miller, MP for Bicester and Woodstock, was informed of the proposed timetable during a meeting with Border Security and Asylum Minister Anna Turley.

The Government reportedly aims to complete its full business case and secure a final ministerial decision before the end of 2026, with construction work potentially beginning in January and the centre opening in April. However, the timetable remains dependent on further surveys, assessments and approval processes, and the Home Office has not formally confirmed an opening date.

Miller has described the proposed timetable as unrealistic, highlighting the lack of existing water and electricity connections, unresolved questions about development costs and uncertainty surrounding the future of military bomb disposal training at the site.

He has also warned that proceeding with construction before Wrong Plan Wrong Site’s ongoing judicial review is heard could put taxpayers’ money at risk, and called for the Government to publish its full business case.

The BBC also reports that the Piddington Community Alliance is raising funds to pursue a separate legal challenge against the recently granted planning permission. The group is seeking £60,000 to support the necessary research and evidence.

The Home Office maintains that former military sites form part of its strategy to reduce reliance on asylum hotels, with accommodation designed to be largely self-contained and supported by round-the-clock security.

For Wrong Plan Wrong Site, the proposed April timetable does not mean the outcome is inevitable. Our existing High Court legal challenge continues, further environmental assessments remain important, and questions about the site’s suitability, infrastructure and overall costs have yet to be fully resolved.

Read our related article: Home Office targets April opening for MOD Bicester despite legal challenge and overwhelming opposition.

More press stories
BBC News: MOD Bicester asylum plans raise concerns over military readiness
BBC News reports concerns from Bicester MP Calum Miller that converting MOD Bicester Site A into asylum accommodation could affect specialist military bomb disposal training and Britain's defence readiness. The Ministry of Defence has confirmed it is assessing alternative training arrangements.
Asylum seeker transport costs exceed £52 million as Government expands use of military sites
The Daily Mail reports that more than £52 million has been spent on transport for asylum seekers across two financial years, including taxis and shuttle buses. The figures raise further questions about the true operational costs of rural asylum accommodation centres such as MOD Bicester Site A.
No results found.

More news

Fire Safety at Site A: Are the Proposed Accommodation Pods Too Close Together?

Fire Safety at Site A: Are the Proposed Accommodation Pods Too Close Together?

The proposal for MOD Bicester Site A includes closely arranged modular accommodation. That immediately raises a practical fire-safety question: how will a fire in one unit be prevented from spreading to another?.
Can 80-Year-Old Concrete Slabs Support Modern Accommodation Buildings?

Can 80-Year-Old Concrete Slabs Support Modern Accommodation Buildings?

Large stretches of MOD Bicester Site A are covered in wartime concrete hardstanding, laid for a very different purpose from modern residential accommodation. Reusing those surfaces may appear economical,.
Democracy is a two-way street. So what happens when the Government stops listening?

Democracy is a two-way street. So what happens when the Government stops listening?

What happens when communities follow every democratic process available to them, yet feel their voices are ignored? With 3,177 objections to MOD Bicester and continued concerns from local councils, Wrong Plan Wrong Site examines ...
No results found.